Approved budget for the bike plan implementation:
- I-280 Channel Trail Feasibility Study (Junipero Serra Trail): $ 250,000
 - UPRRTrail Feasibility Study (De Anza Trail): $ 250,000
 - Bicycle Wayfinding Program: $ 60,000
 - McClellan Road Bike Corridor: $ 5,289,000
 - Bicycle Boulevard Implementation: $ 1,417,000
 - Carmen Road Bridge Feasibility Study: $ 100,000
 - School Walk Audit Implementation: $ 1,250,000Stevens Creek Blvd Class
 - Class IV Lanes Wolfe to Tantau (Apple contribution): $ 1,800,000
Subtotal: $ 10,416,000 
In addition, the current cost estimate for the McClellan Road Bike Corridor as follows: McClellan Road Bike Corridor (estimated)
 Phase 1A: $ 1,982,382
 Phase 1B: $ 908,480
Where:
- Phase 1A is the segment 100’ east of Stelling Rd to Imperial Ave
 - Phase 1B is the signal/intersection improvements at McClellan @ Bubb and McClellan @ Stelling
 - Phase 2 is the segment from Stelling to Torre excluding De Anza Blvd @ McClellan/Pacifica intersection
 - Phase 3 is the segment from Imperial to Byrne
 - Phase 4 is the signal/intersection improvements at De Anza Blvd @ McClellan/Pacifica
 
And:
- Phase 2 and 3 are interchangeable and will depend on ROW acquisition